Updates: 7/19/12

Updated pictures from this week.
Progress continues on the building both inside and outside. We had some really bad rain last week which slowed some things down as it pertains to the roof installation however, we increased the roofers from 8 people to 26 people this week and added another crane. Just yesterday, they completed 3 bays on the lower roof and 1 on the top – if this continues we will hopefully complete the entire roof by the end of the month.

The crews on the inside of the building continue to do a great job, all of the duct work inside is moving very fast as well as the mechanical, electrical and plumbing. The interior walls are really shaping up and you can really begin to see how the interior will flow.